BigWave offers 2 different ways to import scheduling information. The basic schedule import enables you to quickly import schedule dates and requested dates by site id. The advanced schedule import enables you to import the entire schedule including requested dates, scheduled dates and times, and actual dates and times. This article will discuss use of the basic schedule import in a real life project setup scenario.
Basic schedule import enables you to import via a common format found in many spreadsheets that are exchanged between the team in a rollout. This option enables you to open a spreadsheet, enter site id’s in the first column, enter dates in the second column, and upload it.
There are some requirements when working with this type of upload:
a) This import only works for those projects that have one work order per associated site. Older BigWave projects that have more than one work order per site (in a single project) are not able to use the basic schedule import and must use the advanced schedule import.
b) This import only works for schedule dates and work order requested dates and only for date values (not date/time values). If you need to upload actual dates, then the advanced schedule import must be used. If you need to upload date/time values (vs simple date values), then the advanced schedule import must be used.
c) Column A must contain your site id’s.
d) Column’s B, C, and on must match the name of an activity or task you are affecting depending upon your scheduling level setting for your project. For work order requested dates, you must use the column header ‘Requested Date’.
e) Row 1 contains your column headers.
f) Rows 2 and on contain site id’s (Column A) and date values (Columns B and on).
Let’s take a real world scenario.
A project manager is setting up a project in BigWave that contains 100 sites. The sites, already uploaded to the customer master site database, have been brought in and associated to the project.
Once the sites are associated, the PM must create a work order template that will contain the plan to be executed for each site. Each site in this project will go through 3 milestones that are tracked in BigWave. These are Site Survey, Ship Equipment, and Install, and each will become an Activity in the project.
The customer has given us hard dates that for the Surveys and the dates don’t really follow any pattern so these must be either manually keyed or uploaded into the project. Since we don’t want to hand-key 100 dates, we will choose to upload these.
The customer supplied a Requested Date for each site (aka the deadline for when each site must be complete), and rather than hand-key this, we will upload it as well.
The other two activities Ship Equipment and Install may be calculated based upon the Requested Date. We know that the equipment should arrive at least one week before the site is scheduled for installation, so in our model for each site we will make the lead time for Ship Equipment 30 days (just to be safe). The Install activity date is equal to the Requested Date so the lead time for this will be 0 days. You may recall that lead times calculate off the Requested Date. One final note, the duration for each of these activities we set to a single day.
So for this project our work order template will look like the following:

We will never want BigWave to calculate the Site Survey dates, so by leaving Lead Time and Duration blank, BigWave won’t touch these dates when asked to recalculate schedule dates. Lead time for Ship Equipment is set to 30 days, so if the Requested Date for a site is March 15th, then the Ship Equipment activity will calculate to February 14th. Since the duration is one day both the scheduled start and scheduled end dates will be February 14th for this activity. It follows that the Install activity will schedule on March 15th since the lead time is 0 days.
After this simple work order template is set up, the PM is ready to generate the work orders for the project. The PM does so.
100 work orders now belong to the project and the PM is ready to upload the dates. The PM creates a spreadsheet formatted to the above rules (or he can download a preformatted one using Export). The completed spreadsheet looks like the following:

The Site ID’s are in Column A, Columns B and C contain date values for Requested Date and the customer dictated Site Survey date. The rest we will leave up to BigWave.
This upload is accomplished with the Import / Export Center found in the project Setup tab.

The PM chooses the ‘Import’ option and clicks Next (or hit <ENTER> key on the keyboard).

Then the first Schedule import option is chosen. Hit Next (or <ENTER>).

The standard upload file screen is shown. Upload the file and the next screen appears. If you check ‘Map scheduled end dates to start dates’ then the upload dates will affect both the scheduled start and scheduled end value. If left unchecked, only the scheduled start dates will be affected.

Once you hit Next, you are committing the upload and BigWave will import the dates.
Now the PM has date values entered for the Requested Date and Site Survey. There is one final step to completing the project schedule and that is to calculate the Ship Equipment and Install dates. This is done by navigating to the Schedule Options area under the Setup tab. As a side note, notice the Scheduling Level is set to ‘Activity’. This is because the PM is managing this project with Activity items or “at the Activity Level”.

Click the “Click to recalculate the schedule” button to generate the rest of the schedule based upon your Lead Time and Duration values from the work order template.
That’s it! The concepts outlined in this article are directly applicable to the setup of almost any project in BigWave. Your schedule and plan for each site may be much more complex, but the process you follow to get it set up is the same.
Please email us at support@bigwavesoftware.com if you need further explanation on any of these concepts.